Concrete Structures

Practical quantities, clear assumptions and the terms behind them.

ESTIMATING FIELD NOTES

How to approach concrete structures quantities

Concrete takeoffs separate net geometric volume in cubic metres from ordering allowances, bag yields and temporary formwork contact areas. Measure each structural element once so slab, beam and column intersections are never double-counted.

TAKEOFF CHECKLIST
  • Keep net geometric volume separate from wastage and pump or minimum-load allowances.
  • Verify whether formwork includes soffits, sides, end stops or opening deductions.
  • Check product bag yields in cubic metres per bag against the supplier datasheet.
  • Confirm concrete strength class and exposure designation on the structural drawings.
▱↗

Concrete Volume

Slabs, bases and pours. Get the volume right.

Concrete Structures
▱↗

Concrete Cost

Turn your concrete quantity into a material budget.

Concrete Structures
▱↗

Concrete Column

Round or rectangular columns, by the pour.

Concrete Structures
▱↗

Concrete Beam

Concrete and three-sided formwork for beams.

Concrete Structures
▱↗

Concrete Wall

Wall volume and formwork on both faces.

Concrete Structures
▱↗

Concrete Slab

Concrete, bag counts and mesh coverage.

Concrete Structures
▱↗

Concrete Stairs

A solid stepped block, measured tread by tread.

Concrete Structures

Terms for this category

Takeoff (Quantity Takeoff) ↗Measured Works ↗Concrete Grade ↗Rebar (Reinforcement Steel) ↗Wastage Factor ↗Formwork ↗Damp Proof Membrane (DPM) ↗Aggregate ↗Unit Rate ↗Rate Build-Up ↗